Paxtang Parkway Trail Restoration – Construction Closure
Restoration work began on January 6, 2026 on the Paxtang Parkway Trail to improve the long-term safety and reliability of the trail. The work is expected to be complete in the second week of May 2026.
Work Area:
• From Market Street Road for approximately .4 miles
What’s Happening:
• Placement of a new 12-foot trail surface, with 4-foot grass shoulders on both sides
- Replacement of the culvert under the trail
• Replacement of the Kline Plaza sewer line under the trail
• New timber rail fencing and gate
Trail Access:
• Closure is limited to the active construction area
• A posted detour is in place at both trail entrances
• Please respect all physical barriers and signage during construction
Thank you for your patience as these important upgrades are completed. We’ll share updates as work progresses!
Detour is to use 29th Street and 25th Street
See below